September 21-23, 2005

 

ITEM 128-1009-R0905��������������� Planning for Addition to Education Building; The University of Montana-Missoula

 

THAT:�������������������������������������� Consistent with the provisions of MCA 20-25-302, the Board of Regents of the Montana University System authorizes The University of Montana to imple�ment steps necessary to retain a consultant to provide preliminary planning for a new addition to the Education Building.� The schematic planning for this facility will not exceed $75,000.00.� Private donations will wholly fund this project.

 

EXPLANATION:����������������������� The architectural firm selected will provide programming and schematic design solutions and estimates for the proposed addition to the Education building.